Playing by the rules - avoiding a
claim for ineffectiveness
The Public Contracts (Amendment) Regulations 2009 revised the
procurement regulations to create a new remedy of ineffectiveness
empowering the court to declare a contract ineffective. The
court must make such a declaration on the application of the bidder
if any one of three grounds applies, including failure to publish a
tender notice in the Official Journal of the European Union (OJEU),
and certain non-compliances with the Regulations. To avoid an
application for ineffectiveness, authorities should carefully
consider whether the procurement regulations apply to their tender
procedures and if so, ensure proper compliance.
Consequences
A declaration of ineffectiveness runs from the date when the
declaration is made. The Regulations provide that if a
declaration is made, 'obligations under the contract that are yet to
be performed will not be performed'. This wording is taken
from the applicable directive and may mean the contract is treated
as terminated from the date of the declaration and all subsequent
(but not preceding) obligations under it are extinguished.
Potentially harsh consequences could follow for third parties,
(eg sub-contractors or TUPE transferred employees). These
consequences may be remedied by the court's power to 'make any order
that it thinks appropriate' for addressing 'any consequential
matters arising from the ineffectiveness' either when the
declaration is made or any time afterwards. However, a direct
remedy for third parties seems doubtful as the regulations envisage
that the court may use its powers to 'address issues of restitution
and compensation between those parties to the contract who
are parties to the proceedings' (our emphasis).
Contracting parties can agree provisions which will apply between
them if the court makes a declaration. If they do that, the
court will be bound to exercise its powers in a way which is
consistent with their agreement unless it is incompatible with a
declaration of ineffectiveness.
Whenever the remedy of ineffectiveness is imposed, the court must
also make an award of civil damages at a level which is based on the
merits of each case.
Alstom case
In July 2011, Eurostar and Siemens applied to strike out a claim
made by Alstom for a declaration of ineffectiveness under the
parallel (and amended) Utilities Contracts Regulations 2006.
It was held the claim was time barred and that none of the grounds
claimed by Alstom applied. It was not possible to argue that
there had been no OJEU notice merely because there was evidence that
in some respects the contract departed from it. A declaration
of ineffectiveness required (under the first ground) a total absence
of an OJEU notice. Damages were the only remedy available to
Alstom for any proven breaches of the procurement regulations which
caused them loss.
This case illustrates the robust approach which the court is
likely to take, accepting only those cases which fall clearly within
the grounds laid down. Their approach is likely to be welcomed
by contracting authorities and successful bidders as ineffectiveness
is potentially very expensive, involving considerable wasted bid
costs, a wholesale re-tendering, substantial delays, with a wide
range of third parties likely to lose out.
Despite the court's approach, contracting authorities should
still be alert to the pitfalls which may see them fall foul of the
regulations and facing an application for a declaration of
ineffectiveness.
In particular, they should be cautious when deciding whether the
procedures in the Regulations requiring a competition have to be
applied. The following examples are common areas where
mistakes can arise:
Thresholds – where a framework agreement is in place, the
aggregate value of the contract over its full term is used to
determine whether it exceeds the thresholds in the
regulations. Authorities may fail to aggregate the values and
apply the incorrect threshold. This can also happen if works
which have high thresholds are confused with services. The
latter, which can include substantial planned and reactive
maintenance, will still attract far lower thresholds.
Part B services – services categorised as 'Part B' are
largely excluded from the procurement regulations but can be
miscategorised particularly where a contract combines both Part A
and Part B services. Under these circumstances, the services
which account for the majority will dictate the category that
applies.
Teckal exemption – the principle that there is no need to
comply with the procedure if the contract is deemed to be an 'in
house' award. This may be incorrectly applied, for example if
a contracting authority makes an award to a company which it has
established, along with a number of other authorities, to provide
certain services but that company has retained some independence in
the management of its affairs. In this instance the authority
does not exercise a power of decisive influence over both the
strategic objectives and significant decisions of the company.
Negotiated procedure - an authority can negotiate a
contract direct with a bidder in certain circumstances but there
must be a strong justification for this approach.
Material variations – authorities should refer to the
guidance in the Pressetext case to determine whether a proposed
variation requires re-tendering.
Land transactions – whilst land acquisitions and disposals
are generally excluded, development agreements may fall under the
regulations unless acquisition/disposal is the dominant purpose of
the transaction.
To find out more, please contact Rachael
Scarfe |